Map Ta Phut port to see third phase by 2027, IEAT confident

Photo courtesy of Bangkok Post.

Reports from Thailand indicate that the Industrial Estate Authority of Thailand (IEAT) remains optimistic about presenting the third phase of development of the Map Ta Phut deep-sea port in Rayong by the year 2027. The port, a notable part of ongoing development in the Eastern Economic Corridor (EEC), is seen as an essential addition to Thailand’s infrastructure.

Map Ta Phut port progress is reportedly well underway, with key milestones reaching noteworthy completion levels. The governor of the IEAT, Veeris Ammarapala, offered an update on this progress.

“The construction of a sand dam has progressed by 71%; land reclamation is 61% finished and the building of an embankment to protect the shoreline against waves is 39% done.”

This update came during Prime Minister Prayut Chan-o-cha’s recent visit to the construction site of the Map Ta Phut…